A permit is required1 if you're working within 10 metres of a transmission pressure (TP) pipeline, within two metres of an intermediate pressure (IP) pipeline or within a FortisBC right of way.
Note: The current wait time for reviewing and issuing permits is a minimum of four to six months. Permits are processed on a first-come, first-served basis, so please plan your work accordingly.
Please wait. Your application is being submitted...
1Pursuant to the Oil and Gas Activities Act of British Columbia and/or the Statutory Right of Way agreement.