Decision
Argument
BCUC Exhibits
- A-1
Letter dated October 2, 2008 issuing Order No. G‐148‐08 establishing a regulatory timetable to review the Application to Amend Section 2.1 of Rate Schedule 3808 Power Purchase Agreement
- A-2
Letter dated June 25, 2008 to BC Hydro requesting comment on the CON Agreements
- A-3
Letter dated July 14, 2008 to Nelson Hydro granting the request to participate
- A-4
Letter dated July 14, 2008 to Mercer International (Celgar) refusing a request to participate in the process
- A-5
Letter dated July 18, 2008 to FortisBC requesting comments on BC Hydro letter dated July 16, 2008
- A-6
Letter dated July 29, 2008 to Nelson Hydro and FortisBC extending the deadline for responses to August 14, 2008
- A-7
Letter dated August 20, 2008 to BC Hydro requesting a response to the FortisBC and Nelson Hydro submissions
- A-8
Letter dated October 22, 2008 and Order G‐154‐08 amending the Regulatory Timetable and updating the Evidentiary Record
- A-9
Letter dated October 22, 2008 issuing Commission Information Request No. 1 to BC Hydro
- A-10
Letter dated November 4, 2008 amending the Regulatory Timetable in response to a request from Zellstoff‐Celgar (Exhibit C2‐3)
- A-11
Letter dated November 7, 2008 issuing response to request for filing extension (Exhibit C8‐2)
- A-12
Letter dated November 13, 2008, issuing a request to BC Hydro to confirm the context of the spirit of the Power Purchase Agreement with attachments
- A-13
Letter dated November 14, 2008 granting BC Hydro filing extension request
- A-14
Letter dated November 27, 2008 issuing Commission Information Request No. 2 to BC Hydro
- A-15
Letter dated December 10, 2008 amending the Regulatory Timetable in response to Exhibits C2‐7 and C8‐4
- A-16
Letter dated December 19, 2008 denying applications from Zellstoff‐Celgar and the City of Nelson for an Order compelling BC Hydro to respond to certain Information Requests
- A-17
Letter dated December 22, 2008 and Commission Information Request No. 3 to FortisBC Inc. with respect to its Intervenor Evidence
- A-18
Letter dated December 22, 2008 and Commission Information Request No. 4 to Zellstoff Celgar with respect to its Intervenor Evidence
- A-19
Letter dated December 22, 2008 and Commission Information Request No. 5 to Nelson Hydro with respect to its Intervenor Evidence
- A-20
Letter dated January 5, 2009 amending the date for BC Hydro Final Submission and reissuing the Regulatory Timetable
- A-21
Letter L-4-09 dated January 14, 2009 to FortisBC Inc. suspending the review of the City of Nelson Umbrella Agreement pending the Commission’s Decision on the BC Hydro Amend Section 2.1 of Rate Schedule 3808 Power Purchase Agreement Application
Applicant (BC Hydro) Exhibits
- B-1
Letter dated September 16, 2008, filing further comments and an amendment to the Rate Schedule 3808 Power Purchase Agreement
- B-2
Letter dated September 25, 2008 filing comments on the procedural process
- B-3
Letter dated September 30, 2008 filing further comments on the procedural process
- B-4
BC Hydro’s July 16, 2008 response to the Commission’s letter of June 25, 2008
- B-5
Letter dated October 30, 2008 filing responses to Commission Information Request No. 1
- B-6
Letter dated November 5, 2008 filing comments on the request for a further amendment to the Regulatory Timetable (Exhibit C8‐2 & Exhibit C2‐3)
- B-7
Letter dated November 21, 2008 filing responses to Intervenor Information Request No. 1
- B-8
Letter dated November 25, 2008 filing response to the term spirit (Exhibit A‐12)
- B-9
Letter dated December 5, 2008 filing response to the Commissions’ and to the Intervenors’ Information Request No. 2
- B-10
Letter dated December 10, 2008 providing comments in response to applications filed by the City of Nelson (Exhibit C8‐4) and Zellstoff Celgar (Exhibit C2‐7), dated December 8, 2008 and application of Zellstoff Celgar dated December 10, 2008
- B-11
Letter dated December 22, 2008 filing Information Request No. 1 to FortisBC
- B-12
Letter dated December 22, 2008 filing Information Request No. 1 to the City of Nelson
- B-13
Letter dated December 22, 2008 filing Information Request No. 1 to Zellstoff Celgar
Intervenor Exhibits
- C2-1
ZELLSTOFF CELGAR LIMITED PARTNERSHIP ‐ Letter dated October 8, 2008 from Brian Merwin, Director, filing request for Intervenor status and comments
- C2-2
Letter dated July 11, 2008 to the Commission from Celgar requesting to participate
- C2-3
Letter dated November 3, 2008 requesting an extension to the Regulatory Timetable due to the late filing of BC Hydro responses to Commission Information Request No. 1
- C2-4
Email dated November 6, 2008 filing Notice of Counsel and request to be added to the distribution lists
- C2-5
Letter dated November 7, 2008 filing Information Request No. 1 to BC Hydro from K.C. Moller, Sangra Moller, Counsel for Zellstoff Celgar
- C2-6
Letter dated November 28, 2008 from K.C. Moller, Sangra Moller, legal counsel filing Information Request No. 2 to BC Hydro
- C2-7
Letter dated December 8, 2008 from K.C. Moller, Sangra Moller, legal counsel requesting the Commission to extend the time for Intervenor Evidence submissions
- C2-8
Letter dated December 10, 2008 applying for an order pursuant to section 34(3)(b) of the Administrative Tribunals Act compelling BC Hydro to produce responses to Information Requests identified in Schedule A
- C2-9
Letter dated December 11, 2008 issuing further response to BC Hydro letter Exhibit
B‐10
- C2-10
Letter dated December 15, 2008 filing Evidence
- C2-11
Email dated January 2, 2009 filing responses to Commission Information Request No. 4 (Exhibit A‐18)
- C6-1
COMMERCIAL ENERGY CONSUMERS ASSOCIATION OF BC (CEC) – Letter dated October 16, 2008 from Christopher P. Weafer, Owen Bird, legal counsel, requesting Intervenor status
- C6-2
Letter dated November 28, 2008 from Christopher P. Weafer, Owen Bird, legal counsel, filing Information Request No. 2 to BC Hydro
- C6-3
Letter dated December 22, 2008 filing response to City of Nelson Information Request No. 1
- C6-4
Letter dated December 22, 2008 filing response to FortisBC Information Request No. 1
-
C6-5
Letter dated December 22, 2008 filing response to Zellstoff Celgar Information Request No. 1
- C8-1
CITY OF NELSON – Letter dated October 20, 2008 from Karl E. Gustafson, Lang Michener, legal counsel, filing request for Intervenor status
- C8-2
Letter dated November 4, 2008 requesting an extension to the Regulatory Timetable and filing comments
- C8-3
Letter dated November 7, 2008 filing Information Request No. 1
- C8-4
Letter dated October 8, 2008 from K.E. Gustafson, Lang Michener, legal counsel, requesting the Commission to dismiss the Application, or to direct BC Hydro to file responses to those Information Requests which the Utility declined to respond to and extend the deadline for filing Intervenor Evidence
-
C8-5
Letter dated December 11, 2008 from K.E. Gustafson, Lang Michener, legal counsel, requesting Commission reconsider Letter No. L‐57‐08 Exhibit A‐15
-
C8-6
Letter dated December 12, 2008 from K.E. Gustafson, Lang Michener, legal counsel, issuing support of Zellstoff Celgar request
-
C8-7
Letter dated December 15, 2008 filing Evidence
-
C8-8
Letter dated November 28, 2008 from Karl Gustafson, Lang Michener, legal counsel, filing Information Request No. 2 to BC Hydro
-
C8-9
Letter dated January 2, 2009 from Karl Gustafson, Lang Michener, legal counsel, filing responses to Information Requests
Interested Party Exhibits
|
| |
|