Installing gas service

Download the gas service installation application form and:

fax to: 1-888-592-8267 (toll free), 604-592-8267 (local),
call: 1-888-224-2710 option 2.

What information do I need to get started?

New gas service - Include the following when you submit your application:

  • The quantity, BTU load and type of gas appliances to be connected
  • The inlet delivery pressure (available from your natural gas contractor)
  • The name and phone number of your natural gas contractor

New gas meter - Include the following when you submit your application:

  • The quantity, BTU load and type of gas appliances to be connected
  • The inlet delivery pressure (available from your natural gas contractor)
  • The name and phone number of your natural gas contractor

Residential customers:

Minimum scheduling lead times are:

  • Lower Mainland:  3 weeks
  • Interior:  3 – 4 weeks
  • Vancouver Island/Sunshine Coast:  4 – 6 weeks
The above are minimum suggested lead times. Some circumstances may require longer lead times than stated. These circumstances include site visits, permits, or additional design for complex service installations. Please remember, it is always better to apply too early than not early enough.

Builders & developers: new subdivisions, town house complexes, strip malls, residential / commercial mixed use, new mobile home parks.

Note: If a gas main extension is required to service your premise(s) you can expect the lead time to increase to over 13 weeks due to the complexity of the extension.

New Installation

Please submit your application form as soon as possible.

Small commercial customers: restaurant, hairdresser, bakery, auto body shop.

Note: If a gas main extension is required to service your premise(s) you can expect the lead time to increase to over 13 weeks due to the complexity of the extension.

New Installation

Please submit your application form as soon as possible.

Large commercial & industrial customers: industrial, big box retail, institutional.

Note: If a gas main extension is required to service your premise(s)  you can expect the lead time to increase to over 13 weeks due to the complexity of the extension.

New installation

Please submit your application form as soon as possible.
 
 
 