The Mt. Hayes facility is now 90 per cent complete. Testing of the control system is underway, and all operators are hired. The plant remains on schedule to open June 2011.

Site restoration

July – Oct. 2011

Tank and facilities construction

Jan. 2009 – Apr. 2011

Testing and commissioning

Feb. – June 2011

Completed:

  • Construction of gas measurement and odourization station
  • Construction of outer tank
  • Construction of inner tank
  • Electrical substation construction
  • Pipeline connections
  • Pipeline installation