The Mt. Hayes facility is now 90 per cent complete. Testing of the control system is underway, and all operators are hired. The plant remains on schedule to open June 2011.
Site restoration
July – Oct. 2011
Tank and facilities construction
Jan. 2009 – Apr. 2011
Testing and commissioning
Feb. – June 2011
Completed:
- Construction of gas measurement and odourization station
- Construction of outer tank
- Construction of inner tank
- Electrical substation construction
- Pipeline connections
- Pipeline installation